Share Colfax Avenue Streetscape Improvements on FacebookShare Colfax Avenue Streetscape Improvements on TwitterShare Colfax Avenue Streetscape Improvements on LinkedinEmail Colfax Avenue Streetscape Improvements link
Project Purpose
The City of South Bend will be making streetscape improvements to Colfax Avenue to encourage investment, promote safety, calm traffic, and improve the active transportation network.
Project Scope
Streetscape enhancements will be made to Colfax Avenue between the St. Joseph River and Eddy Street. The planned scope is as follows:
St. Joseph River to west of Hill Street (Primary Project Area)
Replacement of curbs, sidewalks, driveway approaches, and street paving
New storm sewer
Raised intersections at Sycamore and Hill Streets with corner pedestrian safety bumpouts
Raised crosswalk with median refuge at East Race
Shared use (pedestrian/bicyclist) path
Pedestrian-scale ornamental lighting
Street trees
Benches
Bike racks
West of Hill Street to Eddy Street (Secondary Project Area)
Street paving
Revisions to lane striping
Targeted driveway approach replacement
Colfax Avenue Bridge Area
In a separate 2026 project, St. Joseph County plans to rebuild the Colfax Avenue bridge over the St. Joseph River and the Colfax Avenue-Dr. Martin Luther King, Jr. Boulevard intersection.
Project Schedule
Construction will occur block-by-block, tentatively beginning spring 2026. Colfax Avenue is to fully reopen to traffic by early September, with full project completion by the end of October.
Property Access
Portions of Colfax Avenue and its intersections will close during construction, but to the degree possible, access to properties will be maintained throughout the project. Use of driveway approaches will be restricted during removal, installation, and the concrete curing period after installation. Every effort will be made to minimize interruption to property access for businesses, residents, and deliveries.
Project Purpose
The City of South Bend will be making streetscape improvements to Colfax Avenue to encourage investment, promote safety, calm traffic, and improve the active transportation network.
Project Scope
Streetscape enhancements will be made to Colfax Avenue between the St. Joseph River and Eddy Street. The planned scope is as follows:
St. Joseph River to west of Hill Street (Primary Project Area)
Replacement of curbs, sidewalks, driveway approaches, and street paving
New storm sewer
Raised intersections at Sycamore and Hill Streets with corner pedestrian safety bumpouts
Raised crosswalk with median refuge at East Race
Shared use (pedestrian/bicyclist) path
Pedestrian-scale ornamental lighting
Street trees
Benches
Bike racks
West of Hill Street to Eddy Street (Secondary Project Area)
Street paving
Revisions to lane striping
Targeted driveway approach replacement
Colfax Avenue Bridge Area
In a separate 2026 project, St. Joseph County plans to rebuild the Colfax Avenue bridge over the St. Joseph River and the Colfax Avenue-Dr. Martin Luther King, Jr. Boulevard intersection.
Project Schedule
Construction will occur block-by-block, tentatively beginning spring 2026. Colfax Avenue is to fully reopen to traffic by early September, with full project completion by the end of October.
Property Access
Portions of Colfax Avenue and its intersections will close during construction, but to the degree possible, access to properties will be maintained throughout the project. Use of driveway approaches will be restricted during removal, installation, and the concrete curing period after installation. Every effort will be made to minimize interruption to property access for businesses, residents, and deliveries.
Page published: 15 Jan 2026, 08:12 AM
View Draft Plans (Coming Soon)
Schedule
Project Design
Colfax Avenue Streetscape Improvements is currently at this stage
Summer 2024 - Spring 2026
Project Bidding & Award
this is an upcoming stage for Colfax Avenue Streetscape Improvements
February-March 2026
Construction
this is an upcoming stage for Colfax Avenue Streetscape Improvements